Jase Manufacturing Co.'s static budget at 7,800 units of production includes $39,000 for direct labor and $3,120 for electric power. Total fixed costs are $43,900. At 10,500 units of production, a flexible budget would show a. variable costs of $56,700 and $43,900 of fixed costs b. variable costs of $56,700 and $59,096 of fixed costs c. variable and fixed costs totaling $86,020 d. variable costs of $42,120 and $43,900

+2
Answers (1)
  1. 22 May, 21:25
    0
    Option A. Variable costs of $56,700 and $43,900 of fixed costs

    Explanation:

    Given:

    Jase Manufacturing Co.'s static budget at 7,800 units of production includes;

    Direct labor = $39,000

    Electric power = $3,120

    Total fixed costs = $43,900

    Variable costs = [$ (39,000 + 3,120) : 7800] * 10,500 = $56,700

    Fixed costs = $43,900
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Jase Manufacturing Co.'s static budget at 7,800 units of production includes $39,000 for direct labor and $3,120 for electric power. Total ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.