Two alternative projects are under consideration: Project A Project B Revenues: $360,000 - 280,000 Variable costs: 210,000 - 180,000 Fixed costs: 90,000 - 90,000 Which of the following is (are) relevant in choosing between the projects? a. Revenues.

b. Variable costs.

c. Fixed costs.

d. Both a and b.

+5
Answers (1)
  1. 10 July, 02:57
    0
    D) Both a and b.

    a. Revenues. b. Variable costs.

    Explanation:

    Project A Project B

    Revenues: $360,000 $280,000

    Variable costs: $210,000 $180,000

    Fixed costs: $90,000 $90,000

    When you are choosing a project, all the information the information is relevant since you must determine the cash flows. In this case, since both projects have the same fixed costs, then they are not as important when determining which project is more profitable.

    We are not told how much does depreciation represent from the fixed costs, but cash flows are calculated by:

    net cash flow = [ (revenues - variable costs - fixed costs) x (1 - tax rate) ] + depreciation
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Two alternative projects are under consideration: Project A Project B Revenues: $360,000 - 280,000 Variable costs: 210,000 - 180,000 Fixed ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.