A production line is to be designed for a job with three tasks. The task times are. 3 minutes, 1.4 minutes, and. 7 minutes. For a single production line with no parallel activities, the minimum cycle time in minutes is:

A. 0.3

B. 0.7

C. 1.4

D. 2.4

E. 0.8

+4
Answers (1)
  1. 26 November, 04:04
    0
    correct option is C. 1.4

    Explanation:

    given data

    task times = 0.3 minutes

    task times = 1.4 minutes

    task times = 0.7 minutes

    to find out

    minimum cycle time in minutes

    solution

    we know that Minimum Cycle time is equal to the length of longest task time

    so here in given task have longest time is = 1.4 minutes

    so here Minimum Cycle time = 1.4 minutes

    hence correct option is C. 1.4
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A production line is to be designed for a job with three tasks. The task times are. 3 minutes, 1.4 minutes, and. 7 minutes. For a single ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.