Next Generation's predetermined overhead rate is $16 per direct labor-hour and its direct labor wage rate is $11 per hour. Job #1987 used $1,202 of direct materials and $5,500 of direct labor.

Question:

If Job #1987 consists of 100 units, what is the average cost assigned to each unit included in the job?

+5
Answers (1)
  1. 23 January, 15:28
    0
    Unitary cost = $147.02

    Explanation:

    Giving the following information:

    Next Generation's predetermined overhead rate is $16 per direct labor-hour and its direct labor wage rate is $11 per hour. Job1987 used $1,202 of direct materials and $5,500 of direct labor.

    First, we need to calculate the allocated overhead to Job 1987:

    direct labor hours = 5,500/11 = 500 hours

    Allocated overhead = 500*16 = $8,000

    Now, we can calculate the total cost and unitary cost of Job 1987:

    Total cost = 1,202 + 5,500 + 8,000 = $14,702

    Unitary cost = 14,702/100 units = $147.02
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Next Generation's predetermined overhead rate is $16 per direct labor-hour and its direct labor wage rate is $11 per hour. Job #1987 used ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.