Marko Shioda, master scheduler at Randall Manufacturing Company, prepared the following MPS for one of the firm's major end products, the Genuine Whatcha Macallit.
Week # 1 2 3
MPS 150 120 50
Mariko is concerned about this schedule's impact on Widgets. It takes 3 Widgets to make each WhatchaMacalit. The two bottleneck work centers for producing Widgets are the "paint" work center and also the "final test" work center. The production manager has indicated that testing each Widget requires 0.3 hours and painting each Widget requires. 5 hours. Calculate the labor hours needed (rough-cut capacity analysis) for the "paint" work center. Week # 1 2 3Widget paint
+2
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Marko Shioda, master scheduler at Randall Manufacturing Company, prepared the following MPS for one of the firm's major end products, the ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Home » Business » Marko Shioda, master scheduler at Randall Manufacturing Company, prepared the following MPS for one of the firm's major end products, the Genuine Whatcha Macallit.