Condor Airplane Company has built a new model jet aircraft which it intends to sell to high net worth clients. This aircraft required 25,000 hours to complete. Condor believes an incremental unit-time learning model with an 82% learning curve best reflects the company's production efficiency. Condor just received a contract to make fifteen identical aircraft. What will be the expected unit time for the sixteenth aircraft?

+1
Answers (1)
  1. 27 December, 07:40
    0
    11,303 Hrs

    Explanation:

    Now here, we can use the learning curve formula, which is as under:

    Y = a * X^ (log of learning rate / log 2)

    Here

    Y is the average time taken by each unit

    a is the time taken by the first unit which is 25000 hrs

    X is the number of units to be produced which is 16 unit (Including the first unit)

    Learning Rate is given and is 82%

    So by putting values we have:

    Y = 25,000 hrs * 16 ^ (Log 0.82 / Log 2)

    Y = 25,000 * 16^ (-0.2863)

    Y = 25,000 * 0.45212 = 11,303 Hrs
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Condor Airplane Company has built a new model jet aircraft which it intends to sell to high net worth clients. This aircraft required ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.