A company bases its predetermined overhead rate on direct labor cost. For next year, total factory overhead cost is estimated at $300,000 and total direct labor cost is estimated at $240,000. For the first month of the year, actual factory overhead cost was $20,000 and actual direct labor cost was $15,000. What amount of overhead will be allocated/applied/assigned to production this month?

+1
Answers (1)
  1. 30 October, 20:52
    0
    Allocated MOH = $18,750

    Explanation:

    Giving the following information:

    The estimated total factory overhead = $300,000

    Total estimated direct labor cost = $240,000.

    The actual direct labor cost was $15,000.

    First, we need to calculate the estimated overhead rate based on direct labor cost. Then, we can allocate overhead.

    To calculate the estimated manufacturing overhead rate we need to use the following formula:

    Estimated manufacturing overhead rate = total estimated overhead costs for the period / total amount of allocation base

    Estimated manufacturing overhead rate = 300,000/240,000 = $1.25 per direct labor dollar

    Allocated MOH = Estimated manufacturing overhead rate * Actual amount of allocation base

    Allocated MOH = 1.25*15,000

    Allocated MOH = $18,750
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A company bases its predetermined overhead rate on direct labor cost. For next year, total factory overhead cost is estimated at $300,000 ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.