The Master schedule input in to the MRP system is focused at different levels depending on the Process strategy. For a repetitive assemble-to-order process operation, the Master schedule is focused at: a. Finished product level b. Material input level c. Module level d. None of the levels listed here

+4
Answers (1)
  1. 6 December, 15:04
    0
    The best answer is"A"

    Finished product level

    Explanation:

    The material requirement plan specifies the quantity and timing of planned order releases and inorder to have a continuous (make-to-stock) operations, the master production schedule must be focused in that finished product level.