At a production level of 5,150 units, a project has total cash costs of $130,789. The variable cost per unit is $11.07, and the depreciation is $8,600. What is the amount of the total fixed costs? a. $56,204.09 b. $65,178.50 c. $78,992.11 d. $73,778.50e. $68,626.67

+1
Answers (1)
  1. 21 August, 06:34
    0
    d. $73,778.50

    Explanation:

    Variable Cost = $11.07 per unit x 5,150 units = $57,010.50

    Total Cost = $130,789

    Fixed Cost = Total Cost - Variable Cost

    Fixed Cost = $130,789 - $57,010.50

    Fixed Cost = $73,778.50

    Since Depreciation is the Fixed Cost and we have been given the Total Cost of the Project, so the Depreciation is already included in the Fixed Cost.

    Hence Total Fixed Cost is equal to $73,778.50.