A project currently in progress has a cost today of $28,205 the estimated cost to complete he project is $11,210, the contract price for the project is $51,500. Using the percentage of completion method of accounting, what is the Revenue earned?

+4
Answers (1)
  1. 17 June, 06:38
    0
    Revenue earned: $36,853

    Explanation:

    Percentage of completion method seeks to calculate the revenue earned by multiplying the total project revenue to the ratio of cost incurred to total cost estimated cost of the project. This is simplified by below calculation:

    Revenue earned = Total project revenue * (Cost incurred / Total estimated project cost)

    Total estimated project cost = Cost incurred + Estimated cost to complete the project

    Total estimated project cost: 11,210 + 28,205 = 39,415

    Revenue earned = 51,500 * (28,205 / 39,415)

    Revenue earned = $36,853
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A project currently in progress has a cost today of $28,205 the estimated cost to complete he project is $11,210, the contract price for ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.