In making a forward pass through a network, activities L, M, and P are immediate predecessors for activity T, which has an activity time of 7. The early start times for activities L, M, and P are 22, 17, and 27, respectively. The early finish times for activities L, M, and P are 29, 27, and 33, respectively. What is the early finish time for activity T?
+2
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “In making a forward pass through a network, activities L, M, and P are immediate predecessors for activity T, which has an activity time of ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.