Vertis Corporation is interested in cutting the amount of time between when a customer places an order and when the order is completed. Details for the first quarter of the year are provided here. Choose the correct answer from the options provided.

Days

Wait time 12

Inspection time 0.6

Process time 6

Move time 0.4

Queue time 8

Compute the manufacturing cycle efficiency (MCE).

+5
Answers (1)
  1. 10 December, 04:39
    0
    Answer:manufacturing cycle efficiency (MCE) = 0.40

    Explanation:

    Solution to solve for the manufacturing cycle efficiency (MCE)

    Manufacturing Cycle Efficiency (MCE) is solved using the following

    Throughput time = Process time + Inspection time + Move time + Queue time

    = 6 Days + 0.6 Days + 0.4 Days + 8 Days

    = 15 Days

    Therefore, the Manufacturing cycle efficiency (MCE) = Process time / Throughput time

    = 6 Days / 15 Days

    = 0.40

    Therefore, the Manufacturing Cycle Efficiency (MCE) will be 0.40
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Vertis Corporation is interested in cutting the amount of time between when a customer places an order and when the order is completed. ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.