Why is the critical path critical?

Select an answer:

• Any delay in the critical path delays the project finish date.

• It represents tasks in which resources are overallocated.

• It represents tasks that are delayed.

• The tasks on the critical path are the most important ones for achieving the project goal.

+2
Answers (1)
  1. 4 July, 02:23
    0
    Any delay in the critical path delays the project finish date.

    Explanation:

    The critical path method is also said to be the critical path analysis.

    It is referred to a set of algorithm which is used to manage the entire activities related to a project.

    The longest activity is identified and the time to complete the activity is measured in a critical path method.

    It includes the activities and their time duration to be modeled upon.

    In case any of the tasks is delayed, the entire project is delayed.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Why is the critical path critical? Select an answer: • Any delay in the critical path delays the project finish date. • It represents tasks ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.