Ask Question
19 August, 07:59

Song, Inc., uses the high-low method to analyze cost behavior. The company observed that at 22,000 machine hours of activity, total maintenance costs averaged $33.40 per hour. When activity jumped to 25,000 machine hours, which was still within the relevant range, the average total cost per machine hour was $30.40. On the basis of this information, the fixed cost was:

a. $550,000.

b. $734,800.

c. $760,000.

d. $184,800.

e. $210,000.

+5
Answers (1)
  1. 19 August, 08:17
    0
    a. $550,000

    Explanation:

    The total maintenance cost at 22,000 machine hours is given as:

    Total maintenance costs=22,000*33.40=$734,800

    The total maintenance cost at 25,000 machine hours is given as:

    Total maintenance costs=25,000*30.40=$760,000

    Variable cost per unit=760,000-734,800/25,000-22,000

    =$8.4 per unit

    Total costs=fixed costs+variable cost

    734,800=fixed costs+8.4*22,000

    Fixed cost=734,800-184,800=$550,000

    So the answer is a. $550,000
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Song, Inc., uses the high-low method to analyze cost behavior. The company observed that at 22,000 machine hours of activity, total ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers