Job 593 was recently completed. The following data have been recorded on its job cost sheet:

Direct materials $2,461

Direct labor-hours 74 labor-hours

Direct labor wage rate $18 per labor-hour

Machine-hours 137 machine-hours

The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $19 per machine-hour. The total cost that would be recorded on the job cost sheet for Job 593 would be:

(A) $3,720

(B) $3,793

(C) $7,236

(D) $6,396

+1
Answers (1)
  1. 11 June, 23:41
    0
    JOB 593

    Total cost of the job

    Direct material 2,461

    Direct labour (74 hrs @ $18) 1,332

    Overhead applied (137 hrs x $19) 2,603

    Total cost of the job 6,396

    The correct answer is D

    Explanation:

    The total cost of the job is the aggregate of direct material cost, direct labour cost and overhead applied. Overhead applied is calculated as overhead application rate multiplied by actual machine hours.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Job 593 was recently completed. The following data have been recorded on its job cost sheet: Direct materials $2,461 Direct labor-hours 74 ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.