Aspen Technologies has the following budget dа ta: Estimated direct labor hours 15,000 Estimated direct labor dollars $90,000 Estimated factory overhead costs $198,000 If factory overhead is to be applied based on direct labor hours, the predetermined overhead rate is
If factory overhead is to be applied based on direct labor hours, the predetermined overhead rate is
a. $2.20 b. $16.50 c. $13.20 d. $7.50?