In a Program Evaluation Review Technique (PERT) / Critical Path Method (CPM) chart, each rectangular box, called a task box, has five sections that contain important information about a task.

+4
Answers (1)
  1. 7 September, 03:47
    0
    a) True

    Explanation:

    It is true that In a Program Evaluation Review Technique (PERT) / Critical Path Method (CPM) chart, each rectangular box, called a task box, has five sections that contain important information about a task.

    By definition, The program evaluation review technique (PERT) and critical path method (CPM) are project management tools useful in planning, scheduling, and managing complex projects.

    The key concept in CPM/PERT is that a small set of activities, which make up the longest path through the activity network, control the entire project.

    The 5 sections that contain important information about a task are:

    1. Task duration or time (T)

    2. Earliest Start (ES)

    3. Earliest Finish (EF)

    4. Late Start (LS)

    5. Late Finish (LF)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “In a Program Evaluation Review Technique (PERT) / Critical Path Method (CPM) chart, each rectangular box, called a task box, has five ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.