Excess Construction Corp. has a $16 million contract to construct a building. The company estimates $10.4 million in costs to construct the building and an expected gross profit of $5.6 million. During the current year, the company incurred $3,120,000 of costs on the contract. Under the percentage-of-completion method, how much will Excess Construction Corp. report as revenue in the current year?
+4
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Excess Construction Corp. has a $16 million contract to construct a building. The company estimates $10.4 million in costs to construct the ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.