Shipments of Product X from a plant to a wholesaler are made in lots of 600. The wholesaler's average demand for X is 100 units per week. Lead time from plant to wholesaler is 4 weeks. The wholesaler pays for the shipments when they leave the plant.
Refer to the instruction above. If the plant reduces its lead time from 4 to 2 weeks and keeps its 600 unit lot size, what is the wholesaler's new total cycle plus pipeline inventories?
A) 300 units
B) 500 units
C) 700 units
D) 200 units
+4
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Shipments of Product X from a plant to a wholesaler are made in lots of 600. The wholesaler's average demand for X is 100 units per week. ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Home » Business » Shipments of Product X from a plant to a wholesaler are made in lots of 600. The wholesaler's average demand for X is 100 units per week. Lead time from plant to wholesaler is 4 weeks. The wholesaler pays for the shipments when they leave the plant.