Leelanau Corporation uses a job-order costing system. The following data are for last year: Work in process beginning balance $ 10,500 Work in process ending balance $ 19,000 Cost of goods manufactured $ 323,000 Direct materials $ 115,000 Direct Labor $ 78,000 Leelanau applies overhead using a predetermined rate. What amount of overhead was applied to work in process last year

+4
Answers (1)
  1. 16 July, 03:16
    0
    The correct answer is $138,500.

    Explanation:

    According to the scenario, the given data are as follows:

    WIP beginning = $10,500

    WIP ending = $19,000

    Cost of goods manufactured = $323,000

    Direct material = $115,000

    Direct labor = $78,000

    So, we can calculate the amount of overhead by using following formula:

    Overheads = Total manufacturing costs - Direct materials - Direct labor

    Where, Total manufacturing cost = Cost of goods manufactured + Ending WIP - Beginning WIP

    = $323,000 + $19,000 - $10,500

    = $331,500

    So, by putting the value in the formula:

    Overheads = $331,500 - $115,000 - $78,000

    = $138,500

    Hence, the amount of overhead is $138,500.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Leelanau Corporation uses a job-order costing system. The following data are for last year: Work in process beginning balance $ 10,500 Work ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers