Total Labor Variance Tico Inc. produces plastic bottles. Each bottle has a standard labor requirement of 0.01 hours. During the month of April, 550,000 bottles were produced using 13,000 labor hours @ $8.50. The standard wage rate is $7.50 per hour. Required: Calculate the total variance for production labor for the month of April. Enter amounts as positive numbers. If required, round your answer to the nearest cent. $

+1
Answers (1)
  1. 4 April, 21:31
    0
    Total variance = 69,250 unfavorable

    Explanation:

    Giving the following information:

    Each bottle has a standard labor requirement of 0.01 hours. During April, 550,000 bottles were produced using 13,000 labor hours for $8.50. The standard wage rate is $7.50 per hour.

    Direct labor efficiency variance = (SQ - AQ) * standard rate

    Direct labor efficiency variance = (5,500 - 13,000) * 7.5 = 56,250 unfavorable

    Direct labor rate variance = (Standard Rate - Actual Rate) * Actual Quantity

    Direct labor rate variance = (7.5 - 8.5) * 13,000 = 13,000 unfavorable

    Total variance = 69,250 unfavorable
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Total Labor Variance Tico Inc. produces plastic bottles. Each bottle has a standard labor requirement of 0.01 hours. During the month of ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.