The master budget of Windy Compay shows that the planned activity level for next year is expected to be 50000 machine hours. At this level of activity, the following manufacturing overhead costs are expected: Indirect labor $720000 Machine supplies 180000 Indirect materials 210000 Depreciation on factory building 150000 Total manufacturing overhead $1260000 A flexible budget for a level of activity of 60000 machine hours would show total manufacturing overhead costs of
a. $1,482,000.
b. $1,260,000.
c. $1,512,000.
d. $1,362,000.
+5
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “The master budget of Windy Compay shows that the planned activity level for next year is expected to be 50000 machine hours. At this level ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.