The use of flexible manufacturing systems, properly sequencing jobs, and properly placing tools will minimize Select one: A. move time. B. inspection time. C. process time. D. setup time.

+1
Answers (1)
  1. 19 November, 17:35
    0
    D. setup time.

    Explanation:

    SET UP time can be defined as the amount of time taken to change a machine from the last part of a production lot to the first good part of the next production lot. In high production systems, the amount of repetitive work accounts for a great part of the lead time of the product, the rest is usually set up time.

    Period required to prepare a device, machine, process, or system for it to be ready to function or accept a job.

    Therefore the use of flexible manufacturing systems, properly sequencing jobs, and properly placing tools will minimize the setup time
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “The use of flexible manufacturing systems, properly sequencing jobs, and properly placing tools will minimize Select one: A. move time. B. ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers