Western Company allocates $10.00 overhead to each unit produced. The company uses a plantwide overhead rate with machine hours as the allocation base. Given the amounts below, how many machine hours does the company expect in department 2?
Estimated: Department 1 Department 2
Manufacturing overhead costs $250,000 $150,000
Direct labor hours 8,000 DLH 12,000 DLH
Machine hours 15,000 MH? MH
a. 33,000 MH
b. 137,500 MH
c. 82,500 MH
d. 25,000 MH
+2
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Western Company allocates $10.00 overhead to each unit produced. The company uses a plantwide overhead rate with machine hours as the ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.