When determining which activity to crash, there are other factors that should be assessed beyond cost. Which of the following is NOT one of these factors? ch9 Select one:a. Resource availability after crashing that activity b. The level of difficulty involved in completing the activity c. The inherent risk associated with the activity d. How crashing will impact the morale and motivation of the individuals working on that activity e. When during the project the activity will occur

+5
Answers (1)
  1. 22 July, 03:04
    0
    B) The level of difficulty involved in completing the activity

    Explanation:

    Since you are considering what activity to crash, then you shouldn't worry about how easy or difficult it is to complete that activity. You have to worry about how fast you can complete that activity. The whole purpose of crashing activities is to save time even if your costs increase or how difficult it is to complete them.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “When determining which activity to crash, there are other factors that should be assessed beyond cost. Which of the following is NOT one of ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers