Ask Question
12 November, 04:22

Archer Construction Company began work on a $420,000 construction contract in 2017. During 2017, Archer incurred costs of $278,000, billed its customer for $215,000, and collected $175,000. At December 31, 2017, the estimated additional costs to complete the project total $162,000. Prepare Archer's journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method

+4
Answers (1)
  1. 12 November, 04:34
    0
    This a loss making contract of $33,000

    Explanation:

    Under I. A. S 11, The following steps are followed

    Step 1 - Determine Expected Outcome of the Contract

    Project Value - 420,000

    Cost to date - (278,000)

    Cost to complete - (175,000)

    Outcome of Contract is Loss of $33,000

    Step 2 - Determine the amounts to be recognized in Income Statement for Profit, Revenue and Cost.

    Cost to date - 278,000

    Contract Loss (33,000)

    Revenue (Balancing Amount = $245,000

    Journal Entries

    Dr Cost expended to date - 278,000

    Cr Revenue to date - 245,000

    Cr Loss 33,000

    b) Percentage Completion Method

    Stage of Completion % = (Costs incurred to Date / Total Contract Costs) * 100

    278,000/453,000 = 61.36%

    Revenue recognizable = 61.36% * Contract Value = 257,712

    Cost to date = ... = 278,000

    Loss to Date (balancing figure) ... = 20,288

    Journal Entries

    Dr Cost expended to date - 278,000

    Cr Revenue to date - 257,712

    Cr Loss 20,288
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Archer Construction Company began work on a $420,000 construction contract in 2017. During 2017, Archer incurred costs of $278,000, billed ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers