Which one of the following is not considered as material costs? a. Partially completed motor engines for a motorcycle plant b. Bolts used in manufacturing the compressor of an engine c. Rivets for the wings of a new commercial jet aircraft d. Lumber used to build tables

+4
Answers (1)
  1. 8 August, 04:45
    0
    A. Partially completed motor engines for a motorcycle plant

    Explanation:

    Material cost is the cost of materials used to manufacture a product or provide a service. It is the cost of the raw materials and the components that are used to manufacture a product. These materials should be easily identifiable with the resulting product.

    Partially completed motor engines for a motorcycle plant is not a material cost because it cannot be directly traced to a particular product
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Which one of the following is not considered as material costs? a. Partially completed motor engines for a motorcycle plant b. Bolts used ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers