Juarez builders incurred $285,000 of labor costs for construction jobs completed during the month of august, of which $212,000 was direct and $73,000 was indirect supervisory costs. the correct journal entry to record the direct labor for the month is: debit work in process inventory $212,000; credit cash $285,000. debit work in process inventory $212,000; credit factory wages payable $212,000. debit factory wages $285,000; credit factory wages payable $285,000. debit payroll expense $212,000; credit cash $212,000. debit factory wages payable $285,000; credit work in process inventory $212,000.

+3
Answers (1)
  1. 28 October, 05:11
    0
    The answer is

    debit work in process inventory $212,000; credit factory wages payable $212,000.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Juarez builders incurred $285,000 of labor costs for construction jobs completed during the month of august, of which $212,000 was direct ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers