Mill Construction Co. uses the percentage-of-completion method of accounting. During 20X5, Mill contracts to build an apartment complex for Drew for $20mn. Mill estimates that total costs would amount to $16mn over the period of construction. In connection with this contract, Mill incurs $2mn of construction costs during 20X5. Mill bills and collects $3mn from Drew in 20X5. What amount should Mill recognize as gross profit for 20x5?
+3
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Mill Construction Co. uses the percentage-of-completion method of accounting. During 20X5, Mill contracts to build an apartment complex for ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.