Shipments of Product X from a plant to a wholesaler are made in lots of 600. The wholesaler's average demand for X is 100 units per week. The lead time from the plant to the wholesaler is 4 weeks. The wholesaler pays for the shipments when they leave the plant. 4. Refer to the scenario above. What is the total of the wholesaler's current cycle plus pipeline inventories

+5
Answers (1)
  1. 13 February, 12:38
    0
    Answer: 1000 is the total wholesaler current cycle plus pipleline inventories.

    Explanation: product X from a plant to a Wholesaler are made in lots of 600. Average demand of X is 100 units per week.

    lead time from the plant is 4 weeks, So we have 100x4 = 400

    600+400=1000
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Shipments of Product X from a plant to a wholesaler are made in lots of 600. The wholesaler's average demand for X is 100 units per week. ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers