Banner Systems is a start-up company that makes connectors for high-speed Internet connections. Banner has budgeted three hours of direct labor per connector, at a standard cost of $ 13 per hour. During August, technicians actually worked 190 hours completing 78 connectors. All 78 connectors actually produced were sold. Banner paid the technicians $ 13.80 per hour. What is Banner's direct labor efficiency variance for August?

+3
Answers (1)
  1. 4 April, 19:43
    0
    572 Favorable

    Explanation:

    Direct Labour efficiency Variance:

    = (Standard Labour Hour - Actual Labour Hour) * Standard Rate

    = [ (78 connectors * 3 hours of direct labor per connector) - (190 hours) ] * $13 per hour

    = [234 hours of direct labor - 190 hours] * $13 per hour

    = 44 hours * $13 per hour

    = $572 Favorable

    Therefore, Banner's direct labor efficiency variance for August is $572 Favorable.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Banner Systems is a start-up company that makes connectors for high-speed Internet connections. Banner has budgeted three hours of direct ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.