4. Explain the purpose of a change control process. Who should be on the committee and often should it meet?

+1
Answers (1)
  1. 17 November, 20:35
    0
    Explained

    Explanation:

    Change control process has a purpose to ensure that the changes are made within a project in a consisted manner and the appropriate stake holders are informed about the state of the product, changes to it and the cost and the schedule impact of these changes. The change control board in a software company often consists of the development manager, the test lead and the product manager (Subject matter expert).