A contractor figured materials for a job would cost $2,415. He also estimated labor for the same job would cost $1,832. If he adds 18% to cover overhead and profit, how much will he charge the customer for this job?

+2
Answers (1)
  1. 12 July, 17:50
    0
    =5, 011.46

    Explanation:

    cost of materials : $ 2,415

    cost of labor: $ 1,832

    Total cost; ($ 2,415+$ 1,832) = $ 4,247

    Add 18 percent mark-up = 4247*1.18

    =5, 011.46
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A contractor figured materials for a job would cost $2,415. He also estimated labor for the same job would cost $1,832. If he adds 18% to ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.