StarQuest plans to introduce a new entertainment package and estimates immediate sales of $300 million. However, due to production conflicts, the product launch may be delayed two years, allowing competition to reduce sales by 10 percent. Using a 6 percent opportunity cost, determine the cost of the delay

+2
Answers (1)
  1. 4 June, 14:19
    0
    The cost of two years' delay is $59.70 million

    Explanation:

    The cost of delay is difference between the sales that ought to have been made if there was no delay and the present of sales when sales is delayed.

    If there was no delay $300 million would have been made.

    The present value of sales when delayed two years is given by the formula below:

    pv=fv / (1+r) ^n

    fv future sales price of $300m * 90% (the effect of 10% reduction in sales)

    r rate is the opportunity of investing at 6%

    n is the number of years of delay, which is 2 years

    PV = ($300*90%) / (1+0.06) ^2=$240.30 million

    The cost of delay = $300m-$240.30m

    =$59.70m
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “StarQuest plans to introduce a new entertainment package and estimates immediate sales of $300 million. However, due to production ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.