Lillian Fok is president of Lakefront Manufacturing, a producer of bicycle tires. Fok makes 1 comma 000 tires per day with the following resources: Labor: 400 hours per day @ $12.50 per hour Raw Material: 20 comma 000 pounds per day @ $1.00 per pound Energy: $5 comma 000 per day Capital: $10 comma 000 per day Labor productivity per labor hour for these tires = nothing tires/labor hour (round your response to two decimal places).

+3
Answers (1)
  1. 26 July, 02:56
    0
    2.5 units per hour

    Explanation:

    Given that,

    Total output = 1,000 tires per day

    Labor = 400 hours per day @ $12.50 per hour

    Raw Material = 20,000 pounds per day @ $1.00 per pound

    Energy = $5,000 per day

    Capital = $10,000 per day

    Labor productivity per labor hour:

    = Total output : Total labor hours

    = 1,000 : 400 hours per day

    = 2.5 units per hour
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Lillian Fok is president of Lakefront Manufacturing, a producer of bicycle tires. Fok makes 1 comma 000 tires per day with the following ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.