For the "determine data needs" activity of a project, the optimistic estimated duration is 10 days, the pessimistic estimated duration is 20 days, the most likely time is 15 days. What is the expected duration of completing this activity?
+3
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “For the "determine data needs" activity of a project, the optimistic estimated duration is 10 days, the pessimistic estimated duration is ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.