The Collins Company forecasts that total overhead for the current year will be $12,000,000 and that total machine hours will be 200,000 hours. Year to date, the actual overhead is $8,000,000 and the actual machine hours are 100,000 hours. If the Collins Company uses a predetermined overhead rate based on machine hours for applying overhead, what is that overhead rate?

+5
Answers (1)
  1. 20 December, 04:48
    0
    Estimated manufacturing overhead rate = $60 per machine hour

    Explanation:

    Giving the following information:

    The Collins Company forecasts that total overhead for the current year will be $12,000,000 and that total machine hour will be 200,000 hours.

    To calculate the estimated manufacturing overhead rate we need to use the following formula:

    Estimated manufacturing overhead rate = total estimated overhead costs for the period / total amount of allocation base

    Estimated manufacturing overhead rate = 12,000,000/200,000

    Estimated manufacturing overhead rate = $60 per machine hour
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “The Collins Company forecasts that total overhead for the current year will be $12,000,000 and that total machine hours will be 200,000 ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.