MC Qu. 34 Niemiec Corporation keeps careful track ... Niemiec Corporation keeps careful track of the time required to fill orders. The times recorded for a particular order appear below: Hour Move time 3.3 Wait time 19.7 Queue time 9.9 Process time 1.7 Inspection time 0.9 The manufacturing cycle efficiency (MCE) was closest to: (Round your intermediate calculation and final answer to 2 decimal places.) Multiple Choice 0.11 0.95 0.19 0.05

+5
Answers (1)
  1. 24 May, 04:14
    0
    0.11 hour

    Explanation:

    According to the scenario, computation of the given data are as follow:-

    Process time represents value added time = 1.7 hours

    Throughput Time = Move Time + Queue Time + Process Time + Inspection Time

    = 3.3 hour + 9.9 hour + 1.7 hour + 0.9 hour = 15.8 hour

    Manufacturing Cycle Efficiency (MCE) = Value Added Time : Throughput Time

    = 1.7 hour : 15.8 hour

    = 0.11 hour

    According to the analysis, the MCE was closest to 0.11 hour.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “MC Qu. 34 Niemiec Corporation keeps careful track ... Niemiec Corporation keeps careful track of the time required to fill orders. The ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.