What must a project manager do before creating a dependency schedule?

A. Identify which tasks must be completed by the project manager.

B. Identify which tasks will involve the most teamwork.

C. Identify which tasks can be skipped.

D. Identify which tasks are primary and which are dependent.

+3
Answers (1)
  1. 13 August, 09:14
    0
    D. Identify which tasks are primary and which are dependent.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “What must a project manager do before creating a dependency schedule? A. Identify which tasks must be completed by the project manager. B. ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.