The following direct materials data pertain to the operations of Wright Co. for the month of December. Standard materials price $5.00 per pound Actual quantity of materials purchased and used 16,500 pounds The standard cost card shows that a finished product contains 4 pounds of materials. The 16,500 pounds were purchased in December at a discount of 4% from the standard price. In December, 4,000 units of finished product were manufactured. Calculate the materials variances. Identify whether the variance is favorable or unfavorable?
+3
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “The following direct materials data pertain to the operations of Wright Co. for the month of December. Standard materials price $5.00 per ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.