Denver company uses a job costing system. The work in process inventory on december 31 consisted of job no. 173 with a balance of $66,200. Job no. 173 has been charged with manufacturing overhead costs of $20,000. Denver allocates manufacturing overhead costs at a rate of 50% of direct labor cost. What was the amount of direct materials charged to job no. 173?

+3
Answers (1)
  1. 21 May, 04:40
    0
    Calculation of amount of direct materials charged to job no. 173:

    It is given that the work in process inventory on December 31 consisted of job no. 173 with a balance of $66,200.

    Job no. 173 has been charged with manufacturing overhead costs of $20,000. Denver allocates manufacturing overhead costs at a rate of 50% of direct labor cost. It means the direct labor cost would be 20,000/50% = $40,000

    Now we can calculate the amount of direct materials charged to job no. 173 as follows:

    Direct material Cost = Total Cost allocated to Job - Direct Labor Cost - Manufacturing Overhead Cost

    = 66200-40000-20000

    = 6200

    Hence, the amount of direct materials charged to job no. 173 is $6,200
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Denver company uses a job costing system. The work in process inventory on december 31 consisted of job no. 173 with a balance of $66,200. ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.