Maple Company uses a job costing system. Maple Company's schedule of cost of goods manufactured showed the following amounts for the month ended August 31. Cost of direct materials used $ 42 comma 600$42,600 Cost of goods manufactured 124 comma 200124,200 Cost of direct labor ($3030 per hour) 76 comma 20076,200 Work in process inventory, August 1 15 comma 50015,500 Manufacturing overhead cost is allocated at the rate of $ 17$17 per direct labor hour. What is the amount of allocated manufacturing overhead costs for August?

+1
Answers (1)
  1. 21 August, 11:11
    0
    Allocated overhead = $43,180

    Explanation:

    Giving the following information:

    Cost of direct materials used $42,600

    Cost of goods manufactured $124,200

    Cost of direct labor ($30 per hour) = $76,200

    Manufacturing overhead cost is allocated at the rate of $17 per direct labor hour.

    Allocated overhead = predetermined overhead rate * actual allocation base

    Allocated overhead = 17 * (76200/30) = $43,180
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Maple Company uses a job costing system. Maple Company's schedule of cost of goods manufactured showed the following amounts for the month ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.