The BEST approach to network representation of a large and hugely complex project is to: Use AOA. Represent all activities and relationships. Use AON. Simplify network logic and reduce it to the most meaningful relationships.

+2
Answers (1)
  1. 14 July, 14:54
    0
    Simplify network logic and reduce it to the most meaningful relationships

    Explanation:

    The above refers to a Logic Network which describes the sequencial activities in a project over a period of time. Here we are able to see which activity logically precedes/comes before or follows the other. The network logic can be used to identify the targets/achievements or the milestones reached in a project. It aids understanding of project workflow, timescale and relationships/dependencies.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “The BEST approach to network representation of a large and hugely complex project is to: Use AOA. Represent all activities and ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers