Ask Question
11 March, 19:56

tems is a start-up company that makes connectors for high-speed Internet connections. BotNet Systems has budgeted three hours of direct labor per connector, at a standard cost of $ 13 per hour. During August, technicians actually worked 192 hours completing 80 connectors. All 80 connectors actually produced were sold. BotNet paid the technicians $ 13.80 per hour. What is BotNet 's direct labor cost variance for August?

+4
Answers (1)
  1. 11 March, 20:18
    0
    -$153.6 Unfavorable

    Explanation:

    As per the given question the solution of direct labor cost variance for August is provided below:-

    Direct labor cost variance for August = (Standard rate - Actual rate) * Actual hour

    = ($13 per hour - $13.80 per hour) * 192 hours

    = - $0.8 * 192 hours

    = - $153.6 Unfavorable

    Here, the actual rate is higher than standard rate so the amount will come into unfavorable and to reach out the direct labor cost variance for august we put the value into formula.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “tems is a start-up company that makes connectors for high-speed Internet connections. BotNet Systems has budgeted three hours of direct ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers