Jackson Company uses activity-based costing to allocate their overhead costs. Setup costs of $850,000 are based on number of batches. Design modification costs of $155,000 are based on number of design changes. Jackson Company has identified 40,000 batches and has 5,000 design changes in their factory. What is the activity rate for setup?
+4
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Jackson Company uses activity-based costing to allocate their overhead costs. Setup costs of $850,000 are based on number of batches. ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.