Secret Prizes Inc. is planning to sell 200 buckets and produce 190 buckets during March. Each bucket requires 500 grams of plastic and one-half hour of direct labor. Plastic costs $10 per 500 grams and employees of the company are paid $15.00 per hour. Manufacturing overhead is applied at a rate of 110% of direct labor costs. Secret Prizes has 300 kilos of plastic in beginning inventory and wants to have 200 kilos in ending inventory. How much is the total amount of budgeted direct labor for March? $1,425 $3,000 $2,850 $1,500

+5
Answers (1)
  1. 4 June, 22:07
    0
    Budgeted direct labour hours

    = 0.5 hour x 200 buckets

    = 100 hours

    Budgeted amount of direct labour

    = 100 hours x $15

    = $1,500

    Explanation:

    There is need to calculate direct labour hour, which is 0.5 hour multiplied by number of buckets budgeted. then, we will determine the budgeted amount of direct labour, which is budgeted direct labour hours multiplied by hourly rate.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Secret Prizes Inc. is planning to sell 200 buckets and produce 190 buckets during March. Each bucket requires 500 grams of plastic and ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers