TB MC Qu. 4-44 Privott, Inc., manufactures ... Privott, Inc., manufactures and sells two products: Product Z9 and Product N0. The company is considering adopting an activity-based costing system with the following activity cost pools, activity measures, and expected activity: Estimated Expected Activity Activity Cost Pools Activity Measures Overhead Cost Product Z9 Product N0 Total Labor-related DLHs $ 339,018 7,900 4,500 12,400 Product testing tests 53,247 1,150 1,250 2,400 Order size MHs 478,608 5,500 5,800 11,300 $ 870,873 The activity rate for the Labor-Related activity cost pool under activity-based costing is closest to:

+4
Answers (1)
  1. 18 June, 21:43
    0
    labour related activity cost per labour hour = $339,018 / 12,400 = $27.34

    Product Z9 = $27.34 * 7900 = $215,987

    Product N0 = $27.34*4500 = $123,031
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “TB MC Qu. 4-44 Privott, Inc., manufactures ... Privott, Inc., manufactures and sells two products: Product Z9 and Product N0. The company ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers