Ask Question
2 March, 07:27

Planning for acquisition support activities and requirements that deal with fielding/deployment should begin as early as the: [Identify life cycle product support activities and requirements that deal with fielding/deployment (e. g., planning, coordination, organizing deployment teams, materiel release).]

A. Materiel Solution Analysis Phase

B. Engineering and Manufacturing Development Phase

C. Operations and Support Phase

D. Production and Deployment Phase

+2
Answers (1)
  1. 2 March, 07:42
    0
    Option A, Materiel Solution Analysis Phase

    Explanation:

    The equipment answer Analysis part assesses potential solutions for a required capability in associate Initial Capabilities Document (ICD) and to satisfy the phase-specific Entrance Criteria for ensuing program milestone selected by the Milestone call Authority.

    The MSA phase is critical to program fulfilment and attaining materiel readiness because it's the first possibility to persuade systems sup-portability and affordability by using balancing technology opportunities with operational and sustainment requirements. During this phase, various options are analysed to select the materiel solution and broaden the Technology Development Strategy (TDS) to fill any era gaps.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Planning for acquisition support activities and requirements that deal with fielding/deployment should begin as early as the: [Identify ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers