Cosi Company uses a job order costing system and allocates its overhead on the basis of direct labor costs. Cosi expects to incur $800,000 of overhead during the next period, and expects to use 50,000 labor hours at a cost of $10.00 per hour. What is Cosi Company's predetermined overhead rate?

+1
Answers (1)
  1. 17 April, 11:10
    0
    160%

    Explanation:

    From the question above Cosi company is expected to incur $800,000 of overhead during the next period.

    They are also expected to use 50,000 labor hours at a cost of $10 per hour

    The first step is to find the estimated direct labor costs

    = 50,000 * $10

    = $500,000

    Estimated direct labor cost = $500,000

    The next step is to find the estimated overhead rate

    Estimated overhead rate = Estimated overhead/Estimated direct labor costs

    = 800,000/500,000

    = 1.6 * 100

    = 160%

    Hence the predetermined overhead rate for Cosi company is 160%
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Cosi Company uses a job order costing system and allocates its overhead on the basis of direct labor costs. Cosi expects to incur $800,000 ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.