Auntie Ann's is making pretzels on an assembly line that they designed. Current output is 800 pretzels per eight-hour shift. If they change the output to 1,200 pretzels per shift, then the productivity will have changed by:
+1
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Auntie Ann's is making pretzels on an assembly line that they designed. Current output is 800 pretzels per eight-hour shift. If they change ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Home » Business » Auntie Ann's is making pretzels on an assembly line that they designed. Current output is 800 pretzels per eight-hour shift. If they change the output to 1,200 pretzels per shift, then the productivity will have changed by: